Our timeline according MSBA Modules
We are currently in Module 4: Schematic Design
2014
2015
2016
2017
2018
04/19 ELHS Statement of Interest Accepted
12/19 MSBA Accepted Feasibility Program
12/21 OPM Hired (Skanska)
05/22 Design Team Hired (JWA/SMMA)
08/22 PDP Report Due to MSBA
02/23 PSR Report Due to MSBA
04/23 MSBA PSR Approval Meeting
08/23 SD Report Due to MSBA
10/23 MSBA Project Scope Budget Approval Meeting